Time taken for process / scrutiny of licenses / registration certificate / renewal / disposal of cases under various labour enactments / industrial safety laws etc., by the Labour Department, Government of Puducherry

Sl.No. Activity / Services Rendered Form to be Submitted Authority / Offices to be Approached Time Limit
Factories Act, 1948
1 Permission / approval of plans for the construction of / extension of factory building and installation of machinery Form IC Chief Inspector of Factories Within One month from the date of receipt of application complete in all respects
2 Registration and grant of licence for the new factories Form 2 Chief Inspector of Factories Within One month from the date of receipt of application complete in all respects
3 Renewal of license of the running factories Form 2 Chief Inspector of Factories Within One month from the date of receipt of application complete in all respects
4 Issue of NOC for the units not covered under any category notified under Section 85(i) of the Factories Act, 1948 Application in plain paper Chief Inspector of Factories Within 7 days from the date of receipt of application
5 Registration and issue of certificate for the use of a boiler under the Indian Boilers Act, 1923 Application in the plain paper accompanied by manufacturers Boilers Book Chief Inspector of Factories and Boilers Within one month from the date of presentation of Boilers and steam pipe line for inspection
6 Renewal of certificate for use of a boiler on the expiry of a period for which it was granted Application in plain paper accompanied by required fees Chief Inspector of Factories and Boilers Within one month from the date of receipt of application
7 Medical examination of workers after remittance of payment of medical examination fee and submission of challan receipt Application in Plain Paper Joint Chief Inspector of Factories and Boilers / Medical Inspector of Factories Within one month from the date of receipt of the application. An average of 100 workers will be examined
8 Cancellation of Registration on the request of the Management Closure report as prescribed in the Rule (2) along with original licence and copy of settlement details if any, with respect to the retrenched workers Chief Inspector of Factories Within One month from the date of receipt of Closure Report and Original License